A microcontroller is being discontinued. The circuit board has already been approved, the control unit works, and the finished product is expected to stay in service for years. The manufacturer has a decision to make: redesign the board, place one final order for the chip, or build the assemblies it will need while all the parts are still available. It’s not just a decision about the chip. It’s about everything that depends on it.

 

Helen Gallwas
Marketing Communication Manager
Contact us

How can manufacturers secure the long-term availability of electronic components?

When a component is discontinued, manufacturers of equipment and systems have three main options: redesign the affected assembly, make a last-time buy and store the original component, or build and store finished assemblies before critical parts become unavailable. The right choice depends on how long production or service needs to continue, whether the assembly can still be built later, and how much time remains before the final order deadline. If a suitable replacement is available, first check whether it can be qualified without a full redesign.

 

Option When it makes sense What to check before deciding
Redesign The product will remain in production for some time, or an update is already planned. What needs to change in the hardware or firmware? What testing and approvals are required? How will you maintain supply until the revised design is ready?
Last-time buy and storage You want to keep the existing design, and the assembly can still be built or repaired later. When is the final order deadline? How many components will you need over the full period? Will the other parts, production capacity and test equipment still be available?
End-of-life production and storage You’ll need finished assemblies later, but you can’t count on another production run. How many assemblies should you build in the final run? How will you store them, check their condition if necessary, and make them available when needed?

A last-time buy secures a stock of components. It does not guarantee that you’ll still be able to build the assembly later. Holding finished assemblies removes that dependency, but you have to commit to a quantity in the final production run and plan storage around the needs of the complete assembly.

Compare costs while all three options are still open

The unit price tells you little on its own. A redesign may involve engineering, prototypes, testing and fresh approvals. A last-time buy ties up capital and adds storage costs, with assembly costs still to come if you build later. End-of-life production brings the final production run forward and adds the cost of storing finished assemblies. Compare all three over the same period, and check how the numbers change if demand turns out higher or lower than expected.

The final order deadline matters because once it passes, you may no longer be able to order the original component through regular channels. Record not only the discontinuation notice, but also the date by which procurement, engineering and quality need to decide. Our guide to obsolescence management for electronic components explains how to spot these risks in your bill of materials before you run out of options.

 

Keep what works

“The most sustainable component is the one that already exists.” That was the opening premise of Maximilian Krane, CEO of btv technologies, at the COGD Obsolescence Forum at electronica on 10 November 2026. For manufacturers of equipment and systems, it raises a practical question: When is it worth keeping an approved design in use, and when is a redesign the better choice?

Keeping an approved design in use can mean that existing components, circuit boards and spare assemblies remain useful instead of becoming obsolete following a design change. But putting parts into storage does not, on its own, prove a reduction in CO₂ emissions. What matters is whether those parts are actually used and what new production or replacement they can reasonably be expected to avoid. Storage, packaging, testing and transport also belong in the comparison.

Compare two realistic scenarios: Without the stock, what would you need to redesign, manufacture or replace? If you keep the existing design in use, what will it take to maintain supply? That comparison is the basis for deciding whether keeping the design makes sense on both cost and environmental grounds.

 

What to check before the next component discontinuation

  1. Which components could be discontinued before production or the promised service period ends? Start with the parts that have no approved replacement.
  2. What will you actually need later? Check whether you need individual components or ready-to-install assemblies. That distinction determines what to buy, build and store.
  3. When do you have to decide? Record the final order date, the approvals you’ll need and the demand assumptions behind your decision. That way, the next team can see why you chose that option.

If you plan to hold components or finished assemblies for future use, agree on how they’ll be stored before placing the final order or starting the last production run. See how btv STORAGE handles long-term storage of electronic components and assemblies

 

Plan for the next component discontinuation

A component is being discontinued, but your product still needs support? We’ll help you work out whether to hold individual components or finished assemblies and what it will take to keep them ready for use.

Discuss long-term Availability

Sebastian Gersmann
Key Account Manager
CHOOSE A TIME
Thomas Hase
Key Account Manager
CHOOSE A TIME
Christian Schoregge
Key Account Manager
CHOOSE A TIME

More articles

Secure programming: Three questions before production starts

Cyberattacks on refrigeration systems show what’s at stake when connected devices are tampered with. What can manufacturers secure during production, and what still needs protection once devices are in use?

Which spare parts should machine builders keep in stock?

Machine builders should start with the repairs they need to support. If a part cannot be sourced in time, they can qualify an alternative, make a last-time buy or hold finished assemblies for service.

Resilience Starts with Critical Components

Transparency is not enough. Awareness, Control and Transformation help manage critical components and dependencies more deliberately.