A machine signals a maintenance need early, giving the service team time to plan the repair. But if the control assembly has been discontinued and no approved replacement is available, the team still can’t carry out the repair. How can machine builders keep critical spare parts available without stocking everything? Start with the repair itself: What will the team actually replace, how long will the machine need support, and which alternatives can the team use?
Which spare parts should machine builders keep in stock?
Not every spare part needs to be held in stock. If a part can be sourced in time for the repair, procurement can order it when needed. A control assembly with no approved replacement available at short notice is a different matter. In that case, service and procurement should decide early how to support future repairs: by qualifying an alternative or keeping a stock of the original part.
How long will the machine need support?
The number of machines in service and the support periods promised to customers help estimate spare parts demand after regular production ends.
What actually gets replaced during a repair?
If field service swaps the entire control unit, a stock of microcontrollers only helps if those chips can still be used to build or repair control units later. Check whether the other components, the right firmware and the necessary test equipment will still be available.
Which alternatives can the service team actually use?
A part that is available to buy is not necessarily approved for use. Engineering and quality teams should check which machine variants it suits and what changes or tests are needed before it can be fitted.
If a component is approaching end of life, our guide to obsolescence management for electronic components explains the options at that stage.
Qualify an alternative, make a last-time buy or store finished assemblies?
| Situation | What to check |
| A successor part is available. | Which machine variants is it already approved for? Can the service team fit it directly, or will it need hardware or firmware changes and further testing? |
| Situation What to check A successor part is available. Which machine variants is it already approved for? Can the service team fit it directly, or will it need hardware or firmware changes and further testing? A critical component is being discontinued, but the assembly can still be built or repaired. | Consider a last-time buy: a final purchase before production ends. Base the quantity on expected service demand and check that the stored components can still be used when needed. |
| Field service replaces complete assemblies, and future production is not assured. | Check whether you can build the assemblies before regular production ends and hold them for future service. Plan suitable storage conditions and any necessary checks from the outset. |
You can combine these options. For example, a limited stock of original parts can cover service needs until a replacement is approved. The right choice supports the repair you’ll actually carry out; it doesn’t just fill a gap on the bill of materials.
In stock is not the same as ready to use
An inventory record shows how many parts you have. It doesn’t tell you whether a component can still be used in production after years in storage or whether an assembly can be fitted straight away. When setting aside electronics for future service, decide how to protect them and how to check their condition if needed. What’s required depends on the parts and how long you plan to store them.
Once you know which electronics you need to keep for future service, see how btv STORAGE handles long-term storage for electronic components and assemblies
Keep critical spare parts available for your machines
Which electronics will you need for service? Where can you use an alternative, and which components or assemblies should you keep on hand? We’ll work with you to find an approach that fits the repairs you need to support and how long your machines will need servicing.