The production date is set. Can we start the job as planned? Do we have all the parts – and are they ready for the line?
A look at the stock figures only gets you so far. Some parts may already be reserved for another order. Others are available but still need preparing before they can go into assembly.
How many parts are available for this order?
Say a production order needs 1,200 units of a component. There are 2,000 in stock, but 1,000 are reserved for another customer project. On paper, there’s plenty. For this order, you’re still 200 short.
That distinction matters for electronics manufacturing services (EMS) providers, especially when they work with both customer-supplied and self-procured material. Two packs can carry the same part number and still be assigned to different customers. Planners need to know which stock they can use, which lot is approved for the job and who can authorise a change in allocation. In this example, they need to find out whether any of the reserved stock can be reassigned or whether to plan for an incoming delivery.
Can the parts go straight onto the line?
Let’s say the missing 200 arrive on time. They’re in trays, but the placement machine is set up to feed them from a reel. The quantity is now right. The parts still can’t go straight into assembly. Both the tape format and the orientation of the parts in the tape need to match the feeder.
Other jobs call for different steps. A lot may need to be inspected or sorted before it can be released. Moisture-sensitive parts may need drying and protective repackaging if the handling requirements call for it. And if a component needs a specific firmware version before placement, pre-programming has to be scheduled too. Which component services are needed before assembly depends on the condition of the material and the requirements of the order.
In this example, it’s just taping. But it still takes time, and that time needs to be in the schedule.
When will the material be ready at the right site?
If one warehouse supplies several plants, planners can work from a shared view of stock. They still need to agree which quantities each site can call off, who releases them and how much time is needed for preparation and transport. The same distinction applies at a single site: knowing when the parts arrive at goods-in doesn’t tell you when they’ll be ready at the line.
With TAK, btv technologies can organise customer-specific stock and call-offs under agreed rules. If parts need inspecting, taping or programming, that work can be scheduled before dispatch. Planners can then work with the date the material is due at the plant in the quantity and format the job requires.
Three checks before production starts
- Is the required quantity allocated and released for this order?
- Are the parts in the condition and format the line needs?
- Is the date they’ll be ready at the designated site confirmed?
An open question doesn’t mean the production date has to move. It tells you what still needs sorting out. In our example, there’s no need to buy more parts. There’s a taping job to schedule.
Further reading: Component supply for EMS providers and contract manufacturers.